Q&A

What is a Daywork sheet?

What is a Daywork sheet?

Introduction. Daywork is a means by which a contractor is paid for instructed work based on the cost of labour, materials and plant plus a markup for overheads and profit. It is generally used when work cannot be valued in the normal way.

Are Quantity Surveyors entitled to reduce the hours included on a signed Daywork sheet if they consider them unreasonable or excessive?

If the parties have agreed that payment is to be made on a daywork basis, the quantity surveyor has no right to reduce the hours and other resources on the sheets.

Do Daywork rates include supervision?

Each rate must include all potential elements of cost including overheads, profit and supervision as well as costs associated with employment of operatives.

What is Prime cost construction?

A prime cost is defined as ‘an item that has not been selected, or whose value is not known, at the time a domestic building contract is entered into and for the cost of supply and delivery of which the builder must make a reasonable allowance in the contract’

Why a bills of quantities is used as a basis for valuation of variations which often occur during the progress of the work?

Bills of quantities are most useful to the contractor when they are prepared in work sections that reflect likely sub-contract packages. This makes it easier for the contractor to obtain prices from sub-contractors and is more likely to result in an accurate and competitive price.

What is included in prime costs?

A prime cost is the total direct costs of production, including raw materials and labor. Indirect costs, such as utilities, manager salaries, and delivery costs, are not included in prime costs. The prime cost equation is equal to the cost of raw materials plus direct labor.

Is Rent a prime cost?

When a company incurs rent for its manufacturing operations, the rent is a product cost. It is common for the rent to be included in the manufacturing overhead that will be allocated or assigned to the products.

What is construction Cost Index?

Definition. Construction Cost Index is an indicator of the average cost movement over time of a fixed basket of representative goods and services related to Construction Industry. It is the monthly measure of Construction Cost movement for the Indian Construction Industry released by CIDC.

How is a Daywork sheet used in a contract?

Daywork and daywork sheets generally fall under ‘daywork procedures’ which are covered in an overarching contract, and a dayworks sheet is used to summarise the costing information from subcontractor to contractor.

Can a contractor change the hours on a dayworks contract?

He cannot however (unless fraud is proven) once it has been agreed to be paid on a dayworks basis, alter or amend the hours duly authorised and signed off by the Contractor’s representative.

How are variations valued in a day work contract?

Most standard forms of contract make provisions for variations to be valued on a daywork basis if the varied work cannot be properly valued by measurement However, few standard forms describe the process for completion, authorisation or submission of dayworks.

Can a sub-contractor refuse to record dayworks?

Many an argument has been had on site about dayworks. Contractors generally dislike them, but Sub-Contractors as you would expect are more much amenable to them. Typically a Sub-Contractor (wanting to make a few extra quid on the project) will agree with the site agent, foreman or engineer that he is to record the work on a daywork basis.